Wednesday, August 4, 2010

August 4th Update!

All the siding is on the house, except for a small area on the front center gable. Most of the garage has been sided as well, except for a few small areas on the tops of the two ends.
All of the drywall is in place and they have began taping.
Hopefully all the taping and sanding will be completed tomorrow so we can start priming and painting this weekend.

Emshoff was also back out this week. They brought some more dirt in and worked on leveling out our yard. Cabinets, counter tops and garage doors have all been ordered and are expected to be delivered and installed soon. The crew from Murray's Fashion Floors will be out tomorrow to take some measurements so we can get our flooring ordered and installed as well.

No comments:

Post a Comment