Friday, September 17, 2010

Thursday, September 16th (Rob's B-day)

Final touches!
Most of the light fixtures have been hung!
The hardwood floor in the foyer and hallway has been installed and looks awesome! The color turned out great and matches the stain I chose for the trim perfectly!
Paramount Plumbing was back out and began the final installation of our plumbing fixtures.
Paramount should be back out one more time to finish up installing the powder room sink, bath tub and kitchen appliances.
Our front door finally came and I LOVE IT! Inspections are to take place over the next few days, and if all goes well we plan to move in next weekend!